Myint & Associates Offshore Supply Base Ltd._Environmental Compliance Certificate (ECC) for Nga Yoke Kaung Offshore Supply Base Project

ຈັດພິມໂດຍ: Open Development Myanmar

The EIA report for Nga Yoke Kaung Offshore Supply Base Ltd. is submitted by the Company to ECD in February 2019. The said EIA report is approved and this ECCis granted to the Company by ECD on 24 April 2019. The objectives of this ECC are to: 1. prevent, minimize, and/or offset adverse environmental and social impacts; 2. confirm the Project commitments and obligations of the project proponent; 3. set standards and performance measures for acceptable environmental performance; 4. perform regular monitoring and reporting; and 5. provide for the ongoing environmental management of the Project.

ແຫຼ່ງຂໍ້ມູນ (1)

ເບິ່ງຕົວຢ່າງຂໍ້ມູນ - ECC for Myint & Associates Offshore Supply Base Project_April 2019

Additional Info

Field Value
ພື້ນທີ່ພູມສັນຖານ (ຂອບເຂດທີ່ຕັ້ງ)
  • ມຽນມາ
ຫົວຂໍ້ Environmental impact assessments
ປະເພດເອກະສານ Contract
ຄູ່ສັນຍາ
  • Myint & Associates Offshore Supply Base Ltd. (M&AOSB)
ໜ່ວຍງານລັດຖະບານ (ຫຼາຍພາກສ່ວນ)
  • ກະຊວງຊັບພະຍາກອນທຳມະຊາດ ແລະ ອະນຸລັກສິ່ງແວດລ້ອມ
ຊື່ສັນຍາສຳປະທານ/ໃບອະນຸຍາດ Environmental Compliance Certificate for Myint & Associate Offshore Supply Base
ຮູບແບບການເປີດເຜີຍຂໍ້ມູນ ປ່ອຍໂດຍບໍລິສັດ
ສັນຍາລິຂະສິດ

No license given

ລິຂະສິດ No
ສະບັບທີ / ຄັ້ງທີ 1
ພາສາຂອງເອກະສານ
  • ອັງກິດ
ແຂວງ
  • ເອຢະວະດີ
ລີ້ງເພື່ອໄປຫາແຫຼ່ງຂໍ້ມູນ https://myintassociatesosb.com/impact-assessments/, https://myintassociatesosb.com/wp-content/uploads/2019/05/MAOSB-ECC-24-April-2019-Certificate.pdf
ຂໍ້ມູນຕິດຕໍ່

U Myo Tin Group General Manager, Myint & Associates Offshore Supply Base Ltd (M&AOSB) Vantage Tower, Pyay Road, Kamayut Township, 11041 Yangon, Myanmar Telephone: +95 1 230 7722 Fax: +95 1 230 7720 Email address: esiafeedback@myintassociatesosb.com

ໄລຍະສັນຍາ 5.0
ຫົວໜ່ວຍຂອງໄລຍະສັນຍາ ປີ
ພັນທະຂອງຄູ່ສັນຍາໃນການຈັດຕັ້ງປະຕິບັດໂຄງການ

The company shall bear full legal and financial responsibility for all adverse impacts and all actions and omissions of itself and its contractors, subcontractors, officers, employees, agents, representatives, and consultants employed, hired or authorized by the company acting for on behalf of the company, in carrying out work on the project.

ພັນທະໃນການປົກປັກຮັກສາສິ່ງແວດລ້ອມ

The Project Proponent shall carry out the Project in accordance with the documents submitted to Ministry including EIA report, the Project commitments in the EIA report, and the Project’s Specific Conditions and Commitments as stated in this ECC, part E.

ເລກທີສັນຍາແບບເປີດ ocds-miumsd-947385c7-c85c-4356-9589-6a80b2bdd750