The project will have an installed capacity of 400 MW to supply electricity to the surrounding provinces as well as for export to Vietnam. The project is Build Operate and Transfer (BOT) type and the investment cost is USD 816.23 million. The main dam length is 8km with crest 83m above the sea level and about 40m above the river. There are 5 turbine units with a capacity of 80MW each.

ແຫຼ່ງຂໍ້ມູນ (13)

ເບິ່ງຕົວຢ່າງຂໍ້ມູນ - Table of content

Additional Info

Field Value
ພື້ນທີ່ພູມສັນຖານ (ຂອບເຂດທີ່ຕັ້ງ)
  • ກຳປູເຈຍ
ຫົວຂໍ້
  • Hydropower dams
  • SDG15 Life on Land
  • SDG7 Affordable and Clean Energy
ປະເພດເອກະສານ Environmental Impact Assessment
ຄູ່ສັນຍາ
  • Electricity of Vietnam
ໜ່ວຍງານລັດຖະບານ (ຫຼາຍພາກສ່ວນ)
  • ລັດຖະມົນຕີກະຊວງບໍ່ແຮ່ ແລະ ພະລັງງານ
ຮູບແບບການເປີດເຜີຍຂໍ້ມູນ ປ່ອຍໂດຍອົງການທ້ອງຖິ່ນທີ່ບໍ່ແມ່ນລັດຖະບານ
ສັນຍາລິຂະສິດ unspecified
ລິຂະສິດ No
ຂໍ້ຈຳກັດໃນການເຂົ້າເຖິງ ແລະ ນຳໃຊ້

By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use.

ສະບັບທີ / ຄັ້ງທີ 1
ພາສາຂອງເອກະສານ
  • ອັງກິດ
ແຂວງ
  • ສະເຕິງແຕຼງ
ຂໍ້ມູນອ້າງອີງຂອງ Metadata 

Metadata last updated on 2018-08-03. For inquiries contact: Open Development Cambodia, Email: contact@opendevcam.net, Website: http://www.opendevcam.net Address: 43 St. 208, Phnom Penh, Cambodia.

ຂໍ້ມູນຕິດຕໍ່

Key Consultants Cambodia

Room no. 684, 6th floor, Building F, Phnom Penh center, Preah Sihanouk Blvd, Khan Chamkarmon, Phnom Penh

ໄລຍະສັນຍາ 37.0
ຫົວໜ່ວຍຂອງໄລຍະສັນຍາ ປີ
ສະຫຼຸບການສ້າງວຽກເຮັດງານທຳ

It will need a peak workforce of 3000 people during the four years of construction period.

ຈຳນວນວຽກທີ່ສ້າງ 3000.0
ພັນທະໃນການປົກປັກຮັກສາສິ່ງແວດລ້ອມ

The company has obligations to mitigate the environmental impact of its project implementation to the maximum. The encroachment to the forest/habitat and hunting of the wildlife are strictly banned. Appropriated mean to maintain fish and other aquatic life re-appearance as existing by creating fish research center. Regularly control the water quality in the reservoir to avoid adverse effect.

ການປົກປັກຮັກສາວັດທະນະທຳສັງຄົມ

Appropriate training course or new skilled and income restoration shall be provided to the local people (boat operators and fishermen). The compensation can be provided in strengthening livelihood program such as new career capacity building, small business fund providing, agricultural support programs.

ສະຫຼຸບກ່ຽວກັບກອງທຶນສິ່ງແວດລ້ອມ

The annual environmental fund is proposed USD 0.5 million and it will be paid yearly to the Ministry of Environment and Forestry Administration of Royal Government of Cambodia to compensate to the forest and wildlife habitat lost by the project. The MoE and FA will use this fund to support forest and wildlife conservation program in the area. This payment is applied to the whole project operation.

ເອກະສານທີ່ກ່ຽວຂ້ອງ
  • Law on Land (2001)
  • Law on Forestry
  • Law on Water Resource​​ Management of the Kingdom of Cambodia
  • Sub-Decree No. 27 on Water Pollution Control
  • Sub-Decree No.72 on the Environmental Impact Assessment Process
  • Law on Environmental Protection and Management of Natural Resources
  • The Constitution of the Kingdom of Cambodia (2008)
ໂຄງການທີ່ກ່ຽວຂ້ອງ

Lower Sesan II: https://data.opendevelopmentcambodia.net/en/dataset/hydropower-2009-2014/resource/4e6d2d95-80e3-4459-ae09-1b9214746c59/detail?map_id=4

ເອກະສານອ້າງອີງສະເພາະ Draft_EIA_Lower_Sesan_2__01.10.2008.pdf
ຄຳສັບຫຼັກ lower,sesan
ເລກທີສັນຍາແບບເປີດ ocds-miumsd-a3fb3508-0270-4249-bdcb-e57d357bc9cc
ວັນທີອັບໂຫຼດ ເມສາ 10, 2019, 09:35 (UTC)