[Draft] Environmental and social impact assessment: Stung Atay hydro-electric BOT project in Veal Veng district, Pursat province
ຈັດພິມໂດຍ: Open Development Cambodia
ແຫຼ່ງຂໍ້ມູນ (14)
ເບິ່ງຕົວຢ່າງຂໍ້ມູນ - 1. Table of content
Additional Info
Field | Value |
---|---|
ພື້ນທີ່ພູມສັນຖານ (ຂອບເຂດທີ່ຕັ້ງ) |
|
ຫົວຂໍ້ | Hydropower dams |
ປະເພດເອກະສານ | Environmental Impact Assessment |
ຄູ່ສັນຍາ |
|
ຊື່ສັນຍາສຳປະທານ/ໃບອະນຸຍາດ | C.H.D (Cambodia) hydropower development Co.,Ltd. |
ຮູບແບບການເປີດເຜີຍຂໍ້ມູນ | ປ່ອຍໂດຍບໍລິສັດ |
ສັນຍາລິຂະສິດ | Creative Commons Attribution |
ລິຂະສິດ | No |
ຂໍ້ຈຳກັດໃນການເຂົ້າເຖິງ ແລະ ນຳໃຊ້ |
By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use. |
ສະບັບທີ / ຄັ້ງທີ | 1 |
ພາສາຂອງເອກະສານ |
|
ແຂວງ |
|
ຂໍ້ມູນອ້າງອີງຂອງ Metadata |
Metadata last updated on 2019-08-28. For inquiries contact: Open Development Cambodia, Email: contact@opendevcam.net, Website: http://www.opendevcam.net Address: 43 St. 208, Phnom Penh, Cambodia. |
ຂໍ້ມູນຕິດຕໍ່ |
SAWAC Consultants for Development |
ເນື້ອທີ່ອະນຸມັດ | 5098.67 |
ໄລຍະສັນຍາ | 30.0 |
ຫົວໜ່ວຍຂອງໄລຍະສັນຍາ | ປີ |
ຫົວໜ່ວຍການຈ່າຍຄ່າທຳນຽມສຳປະທານ | ໂດລາ/ເຮັກຕາ |
ຫົວໜ່ວຍແຜນການນຳໃຊ້ທີ່ດິນ | Ha |
ສະຫຼຸບການສ້າງວຽກເຮັດງານທຳ |
The company plans to recruit staffs and workers. The company gives priority to people living near the project area. During the four-year construction period, there are about 900 people including 500 local residents and 400 Chinese workers. There were 52 workers for the construction of the transmission line from the two power plants to O'Som sub-station, including 4 local residents and 12 Chinese workers. During the 30 years of operation and maintenance, the company recruits 30 people including 19 Cambodian staffs and 11 Chinese staffs and workers. The company plans to recruit 2 Cambodians and 9 Chinese as staffs to manage transmission line from the power tower of Dam 1 to O'Som sub-station. The company plans to recruit 11 people, 2 Cambodian and 9 Chinese as staffs to manage transmission line from power plant of the second dam to O'Som sub-station. |
ສະຫຼຸບການຝຶກອົບຮົມ |
The project owner will provide training courses for staff and workers, especially Cambodian workers such as technical knowledge, safety precautions, laws, regulations, and prevention strategies for communicable diseases. |
ພັນທະໃນການປົກປັກຮັກສາສິ່ງແວດລ້ອມ |
Overseeing the implementation of the environmental management plan of the company is the responsibility of the coalition of the relevant ministries and departments, which will be developed by the project owner together with the Ministry of Environment. This Environmental Protection and Monitoring Team is under the supervision of the Ministry of Environment. |
ສະຫຼຸບກ່ຽວກັບກອງທຶນສິ່ງແວດລ້ອມ |
The cost of environmental restoration is USD 3,091,250.00 for 6 months. USD 1,977,248.00 for water and land conservation, USD 35,200.00 for environmental protection, USD 545,200.00 for wildlife protection, USD 40,000.00 for wildlife rehabilitation, USD 66,400.00 for health protection, USD 50,000 in environmental education, USD 100,000.00 in consulting fees and USD 130,000 for construction and relocation costs. |
ຈຳນວນກອງທຶນເພື່ອສິ່ງແວດລ້ອມລວມ | 3091250.0 |
ໂຄງການທີ່ກ່ຽວຂ້ອງ |
Stung Atay II: https://data.opendevelopmentcambodia.net/km/dataset/hydropower-2009-2014/resource/d75af965-ac97-4f9c-8705-f7ead9b7f66d/detail?map_id=71 |
ເອກະສານອ້າງອີງສະເພາະ | Draft_EIA_CHD_Cambodia_hydropower__00.12.2011.pdf |
ຄຳສັບຫຼັກ | Environmental impact accessment |
ເລກທີສັນຍາແບບເປີດ | ocds-miumsd-96be65c2-66dc-49c0-917b-d0c9831aa7b1 |
ວັນທີອັບໂຫຼດ | ສິງຫາ 28, 2019, 01:40 (UTC) |
ວັນທີດັດແປງ | ຕຸລາ 4, 2021, 09:44 (UTC) |