DWIR_ESIA Report on Twante Canal Improvement Project
Published by: Open Development Myanmar
Data Resources (3)
Data Resource Preview - ESIA of Twante Canal Improvement Project of DWIR
Additional Info
Field | Value |
---|---|
Geographic area (spatial range) |
|
Topics | Environmental impact assessments |
Document type | Environmental Impact Assessment |
Contracting Parties |
|
Government Entity (multiple) |
|
Disclosure Mode | Released by government |
License |
No license given |
Copyright | No |
Access and use constraints |
By accessing this website or database, users agree to take full responsibility for reliance on any site information provided and to hold harmless and waive any and all liability against individuals or entities associated with its development, form and content for any loss, harm or damage suffered as a result of its use. |
Version / Edition | 1 |
Language of document |
|
Province(s) |
|
Links to source | http://www.ecd.gov.mm/?q=policy |
Party's obligation in the implementation of the project |
The project owner shall earnestly carry out all national and local laws, regulations and requirements on environmental protection, clearly define main duties and responsibilities of environmental protection departments of the project, establish and optimize its rules and regulations. |
Environmental protection obligation |
The project commits to precisely follow the discussed mitigation measures for avoiding or reducing such environmental and socioeconomic impacts generated in temporarily or permanently by the Project activities during both the construction and operation phases. |
Socio-cultural protection |
The project commits to engage the affected community and any project stakeholders in, adequate manner and meaningfully consult them for any environmental and social issues related to the project activities. Land acquisition and resettlement action plan, and grievance redress mechanism will also be done. |
Environmental fund summary |
During the construction phase, a budget of about US$ 53,370 equivalents per year will be allocated for monitoring and evaluation of the Project’s environmental and social performance over the construction period of 5 years. During the operational phase, an annual budget of about US$ 25,850 will be allocated for monitoring activities. |